Question:

A project manager has just facilitated the project change control process, which produced 10 approved change requests. Select the process he is likely to perform next?

A Direct and Manage Project Work
Explaination

The project manager and team are likely to execute the work associated with the approved change requests. These approved change requests are implemented through the Direct and Manage Project Work process.