Question:

A project manager is applying a hybrid approach to manage his project. He discusses with the project’s sponsor to update him on progress achieved to date. To aid the discussion, the project manager represents a chart that visually shows how much work remains versus how much time is left for the project. What is the project manager performing?

A A burndown chart
Explaination

A burndown chart shows how much work remains versus how much time is left within a timebox. Examples of timebox include time remaining for the current or a future iteration, or it may reflect time remaining for the project.