Question:

A project manager is dealing with risks or potential concerns related to stakeholder management and is anticipating future problems that may be increased by stakeholders. What process is she displaying?

A Manage Stakeholder Engagement
Explaination

The project manager is performing the Manage Stakeholder Engagement process. This process includes activities such as engaging stakeholders at appropriate stages, managing their expectations through negotiation and communication, addressing risks or potential concerns related to their management and anticipating future issues, and clarifying and resolving issues identified.