header bg

Question:

A project manager is in the process of measuring the extent to which the project is compliant with regulatory standards by conducting an audit. What activity are they practicing?

A Quality assurance
Explaination

According to the PMBOKĀ® Guide, quality assurance, which occurs through the Manage Quality project management process, is most concerned with using project processes effectively. This includes assuring stakeholders that the end result of the project will meet their needs and expectations and that quality requirements are met.