Question:

A project manager is using a predictive approach to operating her project. Recently, she has experienced several adjustments to the project. All of the following lead to a change request, except for which one?

A Updates to project documents
Explaination

Change requests are typically a means of taking corrective or preventive actions or performing defect repairs. Updates to project documents will typically occur as a result of implementing a change request.