Question:

A project manager recently received agreement to crash the schedule. He started negotiating with the head of development to utilize their most senior Java developer. What project management activity is the project manager displaying?

A Controlling resources
explanation

There are several viable options included, most notably controlling the schedule and resources. Since the project manager is currently negotiating for resources, the best option is controlling resources, which are activities that occur through a project management process called Control Resources. As part of this process, the project manager uses their interpersonal and team skills to influence and negotiate for resources.