According to the PMBOK® Guide, this output of the Manage Stakeholder Engagement process is used to facilitate communication with stakeholders.  

A Issue log
Explaination

According to the PMBOK® Guide, the issue log is used to promote communication with stakeholders. The issue log is part of the project documents update output of this process.