After concluding the sprint, the Scrum master, product owner, and team members come together to judge the overall progress and work finished and to review any lessons learned. This presents what kind of meeting?

A A sprint retrospective
Explaination

The question describes a sprint retrospective meeting, which helps the team plan for the next sprint and determine overall progress.