Question:

An Agile project team develops their schedule by pulling features from the backlog reflected on a task board as capacity to take on work becomes available. In some cases, a feature may take two weeks to finish, while in others, it takes more. What type of delivery remedy does this describe?

A Flow-based Agile
Explaination

A team using a flow-based agile approach, such as Kanban, focuses on developing prioritized features from the backlog. As capacity opens, the team pulls the next feature from the backlog and shifts it to the next column of the task board. They move on to the next one.