Calculate the to-complete performance index (TCPI) based on the current EAC, using the following values: BAC = 15,000, AC = 12,000, EV = 10,000, EAC = 17,000.
A
1.0
explanation
The formula for TCPI when targeting EAC is as follows: TCPI = (BAC – EV) ÷ (EAC – AC). Plug in the values to get the following: ($15,000 – $10,000) ÷ ($17,000 – $12,000) = $1.0.