Question:

Choose the best statement that describes the purpose of carrying out activities associated with planning stakeholder engagement?

A To develop approaches to involve project stakeholders based on their needs, expectations, interests, and potential impacts on the project
explanation

According to the PMBOK® Guide, the purpose of the Plan Stakeholder Engagement process is to develop approaches to involve project stakeholders based on their needs, expectations, interests, and potential impacts on the project. This is the second process of the Project Stakeholder Management Knowledge Area.