Question:

Choose the best statement that describes the purpose of carrying out activities associated with planning stakeholder engagement?

A To develop approaches to involve project stakeholders based on their needs, expectations, interests, and potential impacts on the project
explanation

According to the PMBOK® Guide, the purpose of the Plan Stakeholder Engagement process is to develop approaches to involve project stakeholders based on their needs, expectations, interests, and potential impacts on the project. This is the second process of the Project Stakeholder Management Knowledge Area.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

4 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

4 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*