Question:

Contract stages are closely related to the Project Procurement Management Knowledge Area processes. Select three correct answers of the following statements:

A The requirement stage, which establishes the project and contract needs, is related to the Plan Procurement Management process. 
Explaination

The requisition stage is where the procurement documents are prepared (not the Procurement Management process. The two outputs that become inputs are procurement documentation and source selection criteria.