Question:

Corrective actions are taken as a result of which of the following?

A When comparing and monitoring project performance against the baseline
explanation

Corrective actions are taken as a result of comparing and monitoring project performance against the baseline. The baseline is the project management plan. Deviations that are discovered during the course of the project may or may not require corrective actions. Preventive actions are taken to reduce the probability of negative consequences, and defect repairs are submitted to correct product defects.