Question:

Following the analogous estimating technique, how many hours will it take the team to run the cable?

A 13
Explaination

The analogous estimating technique is a form of expert judgment, which uses the actual duration of a similar activity completed on a previous project to determine the duration of the current activity. This means that Alyssa would rely on feedback from the subject-matter expert who noted that in a past similar project it took 13 hours to complete a similar activity.