header bg

Scan QR code or get instant email to install app

Question:

How is the project currently performing according to the schedule and budget?

A The project is behind schedule and over budget.
explanation

To answer this question, you will need to calculate the cumulative SPI and CPI. All values needed to do this have been provided within the question. The formula for calculating SPI, which will tell us how the project is performing according to the schedule, is EV ÷ PV. Plug in the values provided to result in the following: ($59,000 / $70,200) = 0.84. Anything less than 1.0 means that the project is behind schedule. Now, calculate CPI by using the following formula: EV ÷ AC. Plug in the values provided to result in the following: ($59,000 / $64,500) = 0.91. A CPI under 1.0 means that the project is over budget. Therefore, the project is behind over budget. Therefore, the project is behind schedule and over budget.#p.David is a project manager working for a prominent book publishing company. As the most senior project manager within the organization, he often gets the most complex project assignments. As part of his latest project, he reviews the inspection of deliverables, measuring them against documented requirements and acceptance criteria.