header bg

Scan QR code or get instant email to install app

Question:

How is the project currently performing according to the schedule and budget?

A The project is behind schedule and over budget.
explanation

To answer this question, you will need to calculate the cumulative SPI and CPI. All values needed to do this have been provided within the question. The formula for calculating SPI, which will tell us how the project is performing according to the schedule, is EV ÷ PV. Plug in the values provided to result in the following: ($59,000 / $70,200) = 0.84. Anything less than 1.0 means that the project is behind schedule. Now, calculate CPI by using the following formula: EV ÷ AC. Plug in the values provided to result in the following: ($59,000 / $64,500) = 0.91. A CPI under 1.0 means that the project is over budget. Therefore, the project is behind over budget. Therefore, the project is behind schedule and over budget.

Related Information

Comments

Nur Aishah Hussin

1 year ago

grateful for this app. thanks all!

Collins Yaw Mensah

1 year ago

The best pmp prep app to pass your pmp exams

gonzalezfrank

1 year ago

So far my favorite app that I have used to study

Leave a Reply

Your email address will not be published. Required fields are marked *

*