header bg

Question:

If earned value = 500, planned value = 700, and actual costs = 450, which the following is the schedule variance?

A –200
Explaination

To calculate schedule variance, subtract planned value from earned value (SV = EV – PV): $500 – $700 = –$200. A negative schedule variance means that the project is behind schedule.