Question:

In what activity is the project manager engaged in?

A Developing the stakeholder engagement plan
Explaination

The stakeholder engagement plan captures the strategies used to promote productive involvement of stakeholders throughout the project. While the stakeholder engagement plan is a component of the project management plan, identifying the component itself is a more specific and therefore better answer.