The aim of this process is concerned with satisfying the needs of the stakeholders, operating communications with them, addressing issues, managing their expectations, and more, and this process also associates to this area of the PMI Code of Ethics and Professional Conduct.

A Manage Stakeholder Engagement and the Role Delineation Study
explanation