Question:

The project manager facilitates the implementation of approved changes by following the documented change control proceeding. Which of the following is a valid tool or technique to help the project manager in doing this activity?

A Project management information system
Explaination

The project manager is currently performing the Direct and Manage Project Work process. Of the options provided, project management information system (PMIS) is the only tool or technique listed. The change log and approved change requests are inputs to the process, while work performance data is an output.