The project manager is facilitating an exercise with the team by asking questions about the product and forming answers to describe the use, characteristics, and other relevant perspectives of what will be delivered. Which following activity is the team involved?  

A Product analysis 
Explaination

The project team is using the product analysis technique to define the scope of the project.