Question:

This earned value management calculation is the projected or estimated cost performance that the remaining work of the project must accomplish to meet the BAC or EAC.

A TCPI
Explaination

The to-complete performance index (TCPI) is the projected cost performance the remaining work of the project must achieve in order to meet the BAC or EAC.