Question:

This is an instance of which type of dependency?

A Mandatory
Explaination

Notice that the constraint impacts the sequence of events of the project, since the project manager must work around the deadline of providing the necessary parts before the vendor can begin, based on a contractual requirement. Dependencies that result from a physical or contractual requirement are known as mandatory dependencies, or hard logic.