Question:

What did the project manager fail to take?

A Check the resource calendars for team member schedule conflicts
Explaination

It’s clear that the project manager did not check the resource calendars when creating the schedule. Resource calendars contain working and nonworking days of resources. This includes holidays, vacations, and when resources are idle.