header bg

Question:

What is incorrect with this scenario?  

A The project manager is unclear as to the definition of a milestone.   
Explaination

The duration of a milestone is zero, marking a significant point in time—typically the start or completion of a major deliverable. Therefore, “Finish GUI” is not a milestone.