Question:

What might be a good strategy for balancing out performance between the schedule and budget?

A Level out resource usage to further spread out cost over time
Explaination

Based on the performance indexes provided, the project is 10 percent ahead of schedule but over budget. Leveling out resource usage is a strategy used to spread out costs over time. This helps in reducing sudden spikes in spending, although it may lead to lengthening the schedule.