Question:

What technique are they taking to control the schedule?  

A Crashing 
Explaination

Schedule compression uses fast-tracking or crashing compression techniques to bring delayed activities back in line with the plan. Allocating additional resources to critical activities describes the crashing technique; fast-tracking is where you complete two activities in parallel in order to complete the work faster.