Question:
Which action should you do next?
A
You recommend a feasibility study be conducted as a separate project from this one because the outcome of the project is unknown.
Explaination
This is the best answer to this question. This is a high-risk project, and a feasibility study should be conducted as a separate project because the outcome is unknown.