Which of the following describes a resource which has been committed to a project as part of a contract or within the project charter?

A Pre-assignment
Explaination

Pre-assignments occur when individuals have been promised as part of a contract to a customer, or they have been assigned as early as the project charter. In either case, the resource has officially been committed to the project.