Question:

Which of the following is a valid input that a project manager can use to disseminate information to appropriate stakeholders?

A Work performance reports
Explaination

This question references the Manage Communications process, which is responsible for ensuring the timely distribution of project information. Project management plan, project documents, work performance reports, enterprise environmental factors, and organizational process assets are all inputs of the process. The remaining options presented are tools and techniques of the process, not inputs.