Question:

Which of the following is correct regarding this situation?

A You have not accounted for the organization’s standard processes that may impact how you build your team.
Explaination

When building your team, it is important to consider things such as the organization’s recruitment and procurement procedures and processes. You hired your friend on the spot, so important steps in the process could have been missed. Pre-assignment is when resources are assigned prior to the project start.