Question:

Which of the following options explains one of the factors that a project manager spends time developing the project team?  

A To create an open, encouraging environment in which team members can contribute 
Explaination

Engaging in development activities for the team allows the project manager to improve team competencies, team member interaction, and the overall team environment to enhance project performance.