header bg

Question:

Which of the following process groups does this activity associate with?

A Executing
Explaination

The Executing process group is where you should execute the work defined within the plan and implement corrective and preventive actions as they are approved. The primary focus of the Monitoring and Controlling process group is to take measurements and perform inspections to find out whether there are variances in the plan.