Question:

Which of the following you might do in this situation?

A Develop a mitigation plan for installation and setup
Explaination

You should develop a mitigation plan for installation and setup to reduce the probability and/or impact of this risk on the project. Option "Develop a shared response strategy" is not correct because the sharing response strategy is a strategy for positive risks. This is a negative risk to the project.