While performing activities connected with controlling project and product scope, a project manager uncovers scope creep. The scope creep is?

A The uncontrolled expansion of project or product scope
Explaination

According to the PMBOKĀ® Guide, scope creep refers to the uncontrolled expansion of product or project scope without adjustments to time, cost, and resources; in other words, it is scope that has not been approved.