You are in the Planning stage of the project and have just kicked off activities related to the Determine Budget process. In addition to the cost baseline, what is a likely outcome of this activity?

A Project funding requirements
Explaination

The Determine Budget process yields the cost baseline, project funding requirements, and updates to project documents. The project funding requirements represent the total funding requirements and periodic funding requirements of the project.