You are the project manager for Ooh La La Beauty Products. Your project concerns creating a new line of bath products. You also work on the CCB, which has just approved a scope change. You know that all of the following statements are correct except which one?

A Scope changes do not usually impact the project budget.
explanation

Scope changes might affect the schedule, cost, quality, and other processes and should be thoroughly integrated with all the Monitoring and Controlling processes. Scope changes may reduce the project requirements and thus reduce the number or hours needed to complete the project. This, in turn, could cause a reduction in the project budget.