Question:
Common causes of variance that fall outside the acceptable range are difficult to correct and usually require reorganization of the process. Decisions to change the process are not within the project manager’s authority and always require management approval. The rule of seven refers to when seven or more processes fall on the same side of the median; this indicates that an external factor may be influencing the results.
Comments
edenegayle
4 years ago
I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.
nikhildv
4 years ago
This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.
kerbs2CB
4 years ago
This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.