You are worried about the availability of the specialty marble and know that the following are correct. (Select three.)

A The project schedule can influence this process.
explanation

The Plan Procurement Management process can influence the project schedule (and vice versa). The Estimate Activity Resources process, make-or-buy decisions, and the organization’s business cycle may have an impact on the Plan Procurement Management process.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

4 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

4 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*