Question:

You are worried about the availability of the specialty marble and know that the following are correct. (Select three.)

A The project schedule can influence this process.
Explaination

The Plan Procurement Management process can influence the project schedule (and vice versa). The Estimate Activity Resources process, make-or-buy decisions, and the organization’s business cycle may have an impact on the Plan Procurement Management process.