Question:

You have broken the deliverables for your project as follows: Project Management, Design, Build, and Test. The Design deliverable is further separated to include these deliverables: product design document, blueprints, and prototype. Adequate cost and schedule estimates have been used to all the deliverables. Which of the following has happened?  

A Steps 1, 2, and 3 of decomposition have been performed for the Design deliverable. 
explanation

The five steps of decomposition are to identify major deliverables, organize the WBS, decompose the WBS components into lower-level components, assign identification codes, and validate the WBS. No mention was made in the question of assigning identification codes or validating the correctness of decomposition, so not all of the steps have been performed. The first three steps of the decomposition process for the Design deliverable have been performed.

Related Information

Comments

edenegayle

4 years ago

I’m not sure how this app is accurate, simple & effective along with FREE? But I’m so grateful. Getting professional qualifications can be so expensive & daunting to tackle. This test taking, review-type app has been so extremely helpful. The structure of the app is so intuitive. It definitely helps with giving you an understanding of why something is wrong / right & making sure it sticks. Absolutely love it & I'm so grateful.

nikhildv

3 years ago

This app has been a great help, It gives perspective with the answers and that helps you prepare ... thanks for sharing it.

kerbs2CB

3 years ago

This app helped me pass my PMP today. The questions are not exactly as they are on the test but they help you with gaining the knowledge you need to pass the test! And it is free! I would recommend this to anyone studying for the PMP.

Leave a Reply

Your email address will not be published. Required fields are marked *

*