Question:

You work as the project manager for a construction company that is erecting a new city and county office building in your city. Your CCB recently approved a scope change. You know that scope change might come about as an outcome of all of the following except:

A Schedule revisions
Explaination

Scope changes will cause schedule revisions, but schedule revisions do not change the project scope. Project requirements are part of the project scope statement, and therefore option “Changes to the project requirements” is one of the correct responses.