Question:

You work as the project manager for a large software development project. Your project is being displayed under contract, and the project has just been canceled. Which of the following processes should capture the level of completeness of the project?

A Validate Scope
Explaination

When projects end prematurely, the Validate Scope process is where the level of detail concerning the amount of work completed should be documented.