Question:

Your organization is experiencing a shake-up at the top levels of management. Your project team has shown concerns that their project might be canceled due to the changes going on at the top. Sure enough, your project team was accurate in their suspicions. You’ve received notice that the project is canceled. The team has one maintaining deliverable for the project that was scheduled for completion next month. Your next step is to record the work results to date. Which of the following describes the tools and techniques of the process based on this case?

A Inspection and decision-making techniques
Explaination

This question describes the Validate Scope process. The tools and techniques of this process are inspection and decision-making.